For Rooms A121, B101, B102, B103, B104, B105, B106, B107, B108, B109, B111, B121, and B123
The Office of the Environment recommended that both inoperable compressors associated with OAU-3 be repaired. Building Maintenance (HVAC) has reported that a contractor completed a portion of this work, however only three of the four compressors are operational at this time. Building Maintenance reported that three compressors will provide sufficient cooling capacity for all but the most extreme summertime outdoor conditions. Additionally, Building Maintenance reported that reheat has been provided to OAU-3 which should prevent overcooling of the rooms served by this unit in the future.
The Office of the Environment recommended the non-operational compressors associated with OAU-2 be repaired. Building Maintenance (HVAC) reported this work has been completed.