Assessor
Hummy Khan
Date
Outdoor Temperature
43°F
Relative Humidity
42%
Outdoor Dew Point
22°F
Air Handling Unit (Assess representative sample of RTU/AHU, including Portables)
Check | OK | Comments |
---|---|---|
Tag Number | ||
Displayed
|
Yes
|
|
Status | ||
Running
|
Yes
|
Check | OK | Comments |
---|---|---|
Outdoor Pollution | ||
Free from pollution sources w/i 25 ft. (e.g. dumpster, chimney, etc.)
|
Yes
|
|
Louvers and Access Doors | ||
Operating properly
|
Yes
|
|
Deflectors & Screens | ||
Present
|
Yes
|
|
No debris
|
Yes
|
|
Dampers | ||
Outside air damper: no obstructions
|
Yes Work Order Closed by Building Maintenance
|
Inconsistency on the position of the outside air dampers (OADs) from one unit to the other. On some units OADs appear to be 100% open while on others partially open. For example, RTU-1, RTU-2, RTU-3, AHU-1 OADs are 100% open while on RTU-4, RTU-5 and RTU-6 lot less open.
|
Return air damper: no obstructions
|
Yes
|
Check | OK | Comments |
---|---|---|
Clean | ||
No excess dirt, not used for storage
|
Yes Work Order Closed by Building Maintenance
|
Mixing plenum dirty on all units and need cleaning.
|
Insulation | ||
Secure and Clean
|
Yes
|
|
P-Trap (if present) | ||
Charged with liquid
|
Yes
|
Check | OK | Comments |
---|---|---|
Filters | ||
Free of any bypassing
|
Yes
|
|
Correct size
|
Yes
|
|
Free from excessive loading, dampness or odor
|
Yes
|
|
Not collapsed/not fallen off
|
Yes
|
|
Present (not missing)
|
Yes
|
|
Date and initials written
|
Yes
|
|
Heating Coils | ||
Clean, no noticeable leaks, or obstructions
|
Yes
|
|
Cooling Coils | ||
Clean, no noticeable leaks, or obstructions
|
Yes
|
|
Access: Free of any obstructions in area that may affect access
|
Yes
|
|
Condensation: No excess condensation problems
|
Yes
|
|
Blowoff: Free of water from coil blowoff
|
Yes
|
|
Condensate Pan and Drain Line | ||
No visible bacterial or fungal growth
|
Yes
|
|
Clean, no residue, no standing water
|
Yes
|
|
No Overflow, leakage, blockage, or damage
|
Yes
|
|
Proper slope, drain line ok, drainage acceptable, discharge okay
|
Yes Work Order Closed by Building Maintenance
|
RTU-5 and AHU-1 - Broken condensate drain line.
|
Check | OK | Comments |
---|---|---|
Condition | ||
Operational
|
Yes
|
|
No unusual odors, noise, or vibration
|
Yes
|
Check | OK | Comments |
---|---|---|
Heating Central Plant | ||
Boiler operational
|
Yes
|
Check | OK | Comments |
---|---|---|
Thermostat | ||
Thermostat setting acceptable
|
Yes
|
|
Thermostat cover
|
Yes
|
|
Fan Mode Correct
|
Yes
|
|
Space Temperature Acceptable
|
Yes
|
Work Order Number(s)
266532
Issues found durring this assessment have been assigned to the above
work order(s).
The front entrance vestibule gets really cold and the ceiling mounted heater does not appear to be heating.