Finding Type
Visible mold (leak)
Remediation
During off hours, a board approved contractor set up a containment around the shower room, removed mold impacted ceiling materials, and placed air scrubbers equipped with High Efficiency Particulate Air (HEPA) filters within the work area. The air scrubbers were left within the work area until March 13, 2025.
On March 12, 2025, the Office of the Environment confirmed that the mold impacted drywall ceiling was removed. Building maintenance (plumbing and carpentry) was notified that the removal was completed.
Building Maintenance (Carpentry) will install a new ceiling under WO #54804.
Location
Boy's Locker Room Shower
Tracking Number
FXXHMS2025002CEF
Assigned To
Environmental Services
Closed
Yes
Completion Date