Finding: Glenwood Middle School: media center (FXXGMS2019001174)

Finding Type
Miscellaneous finding
Remediation

Building Maintenance (HVAC) is currently working with an Engineer to have the duct work to the media center (including the TV Studio and Computer lab) unit sealed. The exposed fiberglass insulation above the drop-ceiling will be removed during this work. According to Building Services, the insulation is no longer needed due to a recent roof replacement. Physical work will occur during the Summer of 2019. The date provided is an estimated completion date.

Location
media center
Tracking Number
FXXGMS2019001174
Assigned To
Environmental Services
Closed
Yes
Completion Date