Finding: Centennial High School: Various (FXXCHS2022001F78)

Finding Type
Visible mold on surfaces due to elevated relative humidity/dew point
Remediation

The pipe insulation of the impacted chilled water lines were HEPA vacuumed and encapsulated with a mold and mildew resistant coating containing antimicrobial protection product by a Board approved restoration contractor from December 27-29, 2021.  The Office of Environment conducted a post work inspection and determined some further encapsulating was required in room 210.  The contractor is scheduled to complete work during January 2022.

Location
Various
Tracking Number
FXXCHS2022001F78
Assigned To
Environmental Services
Closed
Yes
Completion Date