Finding: Harper’s Choice Middle School: Portable 141 (FXHCMS2022002085)

Finding Type
Visible mold (leak)
Remediation

The impacted drywall was removed on November 16, 2022. The impacted studs and sub-flooring will be replaced with work anticipated to be complete on November 18, 2022. Building Maintenance sealed the former gutter attachment penetration's on November 16, 2022. The slit in the vapor barrier will also be repaired prior to re-installing the drywall. 

Location
Portable 141
Tracking Number
FXHCMS2022002085
Assigned To
Building Services
Work Orders
#261606
(Complete)
Closed
Yes
Completion Date